Chengdu 2020 Metro Expansion

发布时间:2020-09-10 11:23:45

Chengdu’s Metro has become at one with the city as many rely on the subway to get them from point A to B. Hence, the metro has grown to be a reliable, cheap and daily method of travel.

From its inception, Chengdu’s Metro has plans to be even bigger and better. There are currently 389km of subway lines under constructions in Chengdu 2020. Following on from this, the end of 2020 will see the opening of lines 6, 8, 9, 17 and 18. If all stays on schedule, the metro rails will increase to 555km. So, what’s the latest news on these lines? 


Metro Line 18

Phase one of Line 18 (teal color) running from North to South, South Railway Station to Xinglong, will be open by the end of September 2020. Phase 2 of Line 18, expected to be in operation by the end of 2020, and will connect Chengdu's urban area with the new Chengdu Tianfu International Airport. The total length of the line is about 66.83km and 10 stations in total. Phase three and four are for 2021, and include aNorth extension, an even more South extension and a connection to Jianyang South Railway Station.

 

Metro Line 17 

Chengdu Metro Line 17 has entered the test phase. From May 10th and 11th, the Yongyi section of the first phase of Line 17 completed the two-day test successfully. (The test pass rate is 97.78%)

The total length of the first phase of Line 17 is 26.15 kilometers. There are 9 stations in total, including 2 elevated stations and 7 underground stations.


Metro Line 6

All the stations of the first and second phases of Line 6 have been capped, and the tunnel has been opened. With this, a total of 93.99 kilometers of track laying on the mainline has been completed.

11 stations on Line 6 phase 3 are capped and 8 stations and parking lots have begun to enter the construction phase.

The third phase of Line 6 of the rail transit starts at Guandong Station (excluding) and ends at Lanjiagou Station (inclusive). The total length of the line is about 21.96km, all of which are underground lines, with a total of 18 stations, 1 Huilong parking lot, and 1 main substation.


Metro Line 8 

Expecting to open end of 2020. Great news, all stations along Chengdu’s Metro Line 8 are capped after the 1st phase. Moreover, in the 1st phase, Line 8 has capped 11 stations. This also means, the laying of the short track on the mainline was 60.1km, and the long track was 25.225km.


Metro Line 9

Line 9 Phase one runs from Financial City East to Huangtianba Stations and is envisioned to be the second loop line in Chengdu (after Line 7) in the future.

As well as this, upon opening in 2020, it will be the first-ever fully automated ATO GoA 4 metro line in Chengdu. Furthermore, Line 9 uses high capacity Type A 8-car trains.

 

1599705537750904.jpeg